Project information
Construction
Cherryland Community Center

The Cherryland Community Center will provide space for community members of all ages to build social connections, participate in enriching cultural activities, develop life skills, and have fun. The 17,500 square foot Center will include three multi-purpose rooms for activities and classes, a reading/computer room with a satellite Alameda County library, and a large community room. The Center will be owned and constructed by the County in Cherryland, an unincorporated neighborhood in Hayward. The facility will be operated and maintained by the Hayward Area Recreation District (HARD).
- Project Number
10061
- Project Type
Construction
- Estimated Project Completion 100%
- Board Approved Budget $23,789,816
- Stakeholders Community Development Agency; Hayward Area Recreation District
Schedule
- Design Start Date
2011-06-01
- Construction Start Date
2018-04-23
- Estimated Completion Date
2021-09-09
- Delivery Method
Design - Bid - Build
- Project Phase
Close out